Caroline Murray/Recorder staff On-site preparations are under way for the construction of the Mohawk Valley Gateway Overlook, Amsterdam's pedestrian bridge. Demolition of two South Side buildings on Bridge and River streets began Monday.

Advertisement

South Side demo work marks beginning of gateway project

Tuesday, April 08, 2014 - Updated: 10:21 AM

By CAROLINE MURRAY

caroline.murray@recordernews.com

On-site work for the construction of the Mohawk Valley Gateway Overlook is under way.

Preparations began Monday for the $16.5 million state-funded project, starting with the demolition of two buildings on Bridge and River streets at the South Side of the city.

The demolition got off to a rough start.

Around noon, the Amsterdam Fire Department responded to a call that the contracting company, D.A. Collins Construction Co., struck a lateral service gas line, causing a leak.

"As soon as we hit it, you could hear it," state Thruway Authority employee Ken Murray said.

Murray said National Grid recently conducted a routine utility check, clearing the contracting company for demolition. All service lines were marked on the pavement with bright yellow paint -- all but one, which the contractors consequently hit.

AFD Battalion Chief Michael Whitty said the department was first to arrive on the scene, and made the call to National Grid. He said the leak was not serious.

Both Murray and Whitty said National Grid was not aware the line was a service to the building, and did not mark it accordingly.

National Grid shut off the gas, and Murray said crews would resume the demolition immediately.

The demo site will soon transform into the "staging area," where Collins workers will begin constructing the bridge piers, Amsterdam community and economic development director Robert von Hasseln said.

Von Hasseln said two support beams will be built in the middle of the Mohawk River first, and then the platform next.

The bridge will take less than two years to complete once the demolition ends at the end of April, he said.

"The estimated time of completion is in the end of fall 2015," von Hasseln said. "It will go up fast."

Originally, von Hasseln said construction was set to begin last fall, but contract issues held them back.

He is confident, however, the prolonged start will not set the completion goal back any further.

The project is funded by the Rebuild and Renew New York Transportation Bond Act of 2005 -- administered through the state's Thruway Authority and Canal Corp.

Recently, von Hasseln said he discovered that London is also constructing a bridge similar to the overlook.

Von Hasseln said when completed, the local bridge will be comparable to the "Walkway Over the Hudson" project in the city of Poughkeepsie, which draws more than 700,000 tourists annually.

"We are less than two years out to what will be a major regional attraction," he said.

In addition to serving as a pedestrian walkway, the structure will be a self-guided museum and garden, with allegorical art sculptures, landscaping, plantings, historical labels and signs.

The signs will not only tell the story of Amsterdam, but the history of the Mohawk Valley.

Artistic elements such as compass-like seals will be plastered across the walkway on benches and planters.

Each seal will have a story icon on it, relating to a piece of history that the visitors can read as they stroll through the gardens.

That includes history of the Mohawk Indians, early settlers, modern immigrants, early industry water power, the Erie Canal and Mohawk River.

"It is a whole experience," von Hasseln said.

When the bridge is completed, two large circular story markers will be placed at either end.

These story markers are not being funded by the state's bond because of the added expense.

Instead, Mayor Ann Thane and von Hasseln are looking for grants to pay for an allegorical statue of the sprit of the Mohawk on the north side, and a steel globe on the south.

     

Comments made about this article - 0 Total

Comment on this article

Advertisement
Subscribe to The Recorder

 

The Recorder Sports Schedule

Most Popular

    Area high school sports calendar
    Wednesday, August 24, 2016

    Auto recycler faces code violation, seeks special use permit
    Friday, August 19, 2016

    Settling in at GASD: Ramos talks life, career, education philosophies
    Saturday, August 20, 2016

    Legislature may vote on solar agreement Tuesday
    Monday, August 22, 2016

    Summerfest to celebrate East End park, connect residents to resources
    Friday, August 19, 2016

    Job growth in county on the rise for 2016
    Saturday, August 20, 2016

    Choosing the right district attorney
    Saturday, August 20, 2016

    William Henry Parker
    Tuesday, August 23, 2016

    Richard A. Zientek
    Friday, August 19, 2016

    Aldermen consider outsourcing city bus transportation
    Monday, August 22, 2016

Advertisement

Copyright © McClary Media, Inc.

Privacy Policies: The Recorder

Contact Us

Twitter

Instagram

Facebook